In part 3 of my 13-part series on process manufacturing in Microsoft Dynamics 365 Business Central, I build a production bill of materials (BOM) for a gallon of interior latex paint. Think of the BOM as the recipe Business Central uses to work out which materials a production order needs, and how much of each.
How to create a production BOM
- Open Production BOMs and choose New. Give the BOM a number and a description that identifies what it makes.
- Set the output unit of measure. In this example the basis is one gallon of finished paint. Decide whether your own BOM describes one finished unit or a defined batch before filling in the lines.
- Add the components. For each ingredient, select Item as the line type, choose the item in No., and check its unit of measure. Enter the amount needed for that output basis in Quantity per.
- Certify and assign the BOM. Review the lines, set Status to Certified when the BOM is ready, and select it in Production BOM No. on the finished item’s card.
- Check a test order. In a sandbox, create and refresh a production order for a known quantity. Compare the planned components and units against what you expect before using the setup for live planning.
The detail I’d double-check: what does one mean?
A gallon of finished paint is the output. The ingredients can each have their own unit of measure. A quantity that looks right on its own can still be wrong if it was calculated for a whole batch and entered as though it were for one gallon. Check the finished output unit and each ingredient unit before you trust the component requirements.
For the standard fields and options, see Microsoft’s production BOM guide.